Dam Sluice Gate

Burrendong Dam

The refurbishment of the Sluice Gate at Burrendong Dam was undertaken from June to Sept 2008 for the NSW State Water Corporation.

The work floor was 13m below the top of the Intake Tower which was accessed by the existing 110m long structural steel bridge.

The Sluice Gate is a 24tonne Structutral Steel that can be lowered 35m on guide rails to seal off a water discharge tunnel.

The work included:

Please click on an thumbnail to start the photogallery...

Intake Tower Access BridgeAbrasive Blasting Hoisting EquipmentGate-Before RefurbGate After Refurb
Clevices Sterms Before RefurbClevices Sterms After RefurbComponents  After RefurbSpark Testing New Paintwork