Sewer
Troy
The upgrade of the Troy Sewer Treatment Plant at Dubbo included the construction of an in-ground concrete Effluent Pump Station.The work was undertaken on a confined site within the existing treatment plant and included:
- Earthworks and excavations up to 5m deep
- Construction of heavily reinforced concrete floor, walls and roof to the Wet Well, 4.5m dia x 5.2m deep.
- Construction of a second Wet Well 2.7 dia x 6m deep and Associated Valve Pits.
- Installation of all DN300 and DN150 DICL Pipe, Valves and Fittings.
- Installation of all mechanical items including 5 x Submersible Pumps and all Electrical, Control & Telemetry components of the system.
- Fabrication and installation of all Metal work items.
Please click on an thumbnail to start the photogallery...
Wellington
The No.1 Sewer Pump Station was refurbished in 2005 for Wellington Council.The Wet Well was isolated and bypassed during the construction phase by installing a temporary twin pump arrangement with level controllers and VSD's
Please click on an thumbnail to start the photogallery...